The complete block paving construction process, step by step

From site preparation to turnkey handover – every stage in detail

Step 1 – Preparation and planning

Every successful paving job starts with thorough preparation:

Practical rule: 70–80% of defects come not from the paver but from a poor subgrade, an under-designed base, a waterlogged structure or weak edge restraints.

Keep in mind: depending on the scope of the works, a minor works licence (licencia de obra menor) or a prior notification at the town hall may be required; any work on public land needs municipal authorisation.

Step 2 – Earthworks and formation level

  1. Removal of topsoil, silt and organic matter (typically 20–40 cm).
  2. Replacement of weak soil with granular material.
  3. Shaping the formation level to the designed falls.
  4. Compacting the formation with a plate compactor or roller.
  5. Replacing soft spots with granular material.
  6. Where necessary, a geotextile to separate the subgrade from the sub-base.
  7. Under heavy loads a geogrid can be used to improve bearing capacity.

The compaction requirement for the formation (Ev2 modulus, plate load test) is set in line with the Spanish PG-3 specifications and technical recommendations for pavements; check the current values applicable to your project.

Step 3 – Building the sub-base

Typical materials:

Placing:

Step 4 – Edge restraints (a key element!)

The functions of the kerb:

Kerb types:

Execution: kerbs must be set on a concrete bed with concrete haunching behind. Without edge restraint, the pavement creeps apart and the edges sink.

Step 5 – Bedding layer

The bedding layer is the levelling, load-spreading layer directly under the blocks:

Typical mistakes:

Step 6 – Laying the blocks

Laying patterns:

Cut with a diamond blade or block splitter. Avoid cut pieces smaller than 1/3 of a block in heavily loaded zones.

Step 7 – Jointing and compaction

  1. Sweeping in dry, clean jointing sand or fine grit.
  2. First sweep – make sure the joints are completely filled.
  3. Plate compaction with a rubber mat (without the mat it is forbidden – it damages the blocks).
  4. Re-jointing – the joint material settles.
  5. A top-up a few weeks later is recommended.

Without compaction the surface never beds in properly – the blocks rock and shift.

Plant and tool list

Machinery:

Hand tools:

Weather and seasonal constraints

In the province of Málaga paving can be carried out practically all year round, but a few rules should be respected: