Step 1 – Preparation and planning
Every successful paving job starts with thorough preparation:
- site survey and measurement, locating buried utilities,
- assessing bearing capacity and drainage conditions,
- setting out the formation level,
- determining the falls,
- setting out kerbs, drainage channels and gullies,
- planning the removal of weak, organic, fill or waterlogged soil.
Keep in mind: depending on the scope of the works, a minor works licence (licencia de obra menor) or a prior notification at the town hall may be required; any work on public land needs municipal authorisation.
Step 2 – Earthworks and formation level
- Removal of topsoil, silt and organic matter (typically 20–40 cm).
- Replacement of weak soil with granular material.
- Shaping the formation level to the designed falls.
- Compacting the formation with a plate compactor or roller.
- Replacing soft spots with granular material.
- Where necessary, a geotextile to separate the subgrade from the sub-base.
- Under heavy loads a geogrid can be used to improve bearing capacity.
The compaction requirement for the formation (Ev2 modulus, plate load test) is set in line with the Spanish PG-3 specifications and technical recommendations for pavements; check the current values applicable to your project.
Step 3 – Building the sub-base
Typical materials:
- 0/32, 0/45, 0/56 crushed stone (aggregates to UNE-EN 13242),
- stabilised granular base,
- sandy gravel only for light duty, with a suitable grading,
- cement-treated base (soil-cement / lean concrete) for heavier loads,
- open-graded crushed stone for permeable pavements.
Placing:
- spreading in layers (max. 15–25 cm compacted layer thickness),
- keeping to the optimum moisture content,
- compaction with a vibrating roller or heavy plate compactor,
- level checking with a laser or string line.
Step 4 – Edge restraints (a key element!)
The functions of the kerb:
- lateral restraint – the blocks only hold their position against a stable kerb,
- transferring loads to the ground,
- preventing the pavement from "spreading" apart.
Kerb types:
- garden edging (private properties),
- road kerb (trafficked areas),
- dropped kerb (vehicle crossings, accessibility),
- kerb with drainage channel (an inclined unit beside the pavement that collects and carries rainwater – standard practice in Spanish urbanisation works),
- concrete haunching (concrete collar).
Execution: kerbs must be set on a concrete bed with concrete haunching behind. Without edge restraint, the pavement creeps apart and the edges sink.
Step 5 – Bedding layer
The bedding layer is the levelling, load-spreading layer directly under the blocks:
- Material: washed grit, e.g. 2/5 or 4/8 mm fraction.
- Thickness: 3–5 cm after compaction – no more!
- Important: the bedding must not be pre-compacted separately; it takes its final set together with the blocks during final vibration.
Typical mistakes:
- Using sand under heavier loads: it washes out and silts up.
- Too thick a bedding (6–10 cm): rutting, undulation, settlement.
- Pre-compaction: the bedding gets squeezed apart during laying.
Step 6 – Laying the blocks
- Always lay from the finished surface, onto the prepared bedding.
- Use a string line, laser or screed rails for precise levels.
- A 3–5 mm joint is generally needed; blocks knocked tightly together can spall.
Laying patterns:
- Stretcher bond: suitable for pedestrian or light loading.
- Herringbone: better under vehicle traffic; it distributes shear forces more effectively.
- Interlocking industrial pavers: for high shear forces and industrial applications.
Cut with a diamond blade or block splitter. Avoid cut pieces smaller than 1/3 of a block in heavily loaded zones.
Step 7 – Jointing and compaction
- Sweeping in dry, clean jointing sand or fine grit.
- First sweep – make sure the joints are completely filled.
- Plate compaction with a rubber mat (without the mat it is forbidden – it damages the blocks).
- Re-jointing – the joint material settles.
- A top-up a few weeks later is recommended.
Without compaction the surface never beds in properly – the blocks rock and shift.
Plant and tool list
Machinery:
- mini excavator, loader, dumper,
- plate compactor with rubber mat, reversible plate compactor,
- vibrating roller,
- water-cooled cutting saw,
- laser level or rotating laser.
Hand tools:
- shovel, rake, wheelbarrow,
- string line, stakes, marking spray,
- spirit level, laser level,
- screed bar, screed rails,
- rubber mallet, broom, block lifter,
- manual block splitter or diamond-blade cutter.
Weather and seasonal constraints
In the province of Málaga paving can be carried out practically all year round, but a few rules should be respected:
- Never spread the sub-base on a waterlogged or softened formation – after the torrential autumn rains (DANA episodes) the ground must be allowed to dry out.
- Bedding and jointing should not be carried out during heavy rain.
- In high summer heat it is better to work in the cooler hours; the concrete for kerbs needs curing and protection against drying out.
- In the inland comarcas (Ronda, Antequera) occasional light frosts occur in winter: do not work on frozen ground, although these episodes are rare and short.