Why does quality control matter?
The durability of a block pavement is not decided at the moment of laying – it is decided by whether every single layer was built with the right material, the right compaction and the right levels and falls. Quality control is therefore a continuous process that runs from the arrival of the materials to the handover of the finished pavement.
On public and urbanisation works, quality control is mandatory and documented – but it is advisable for private clients too: one compaction test and one material certificate can save the cost of a major repair a few years down the line.
1. Checking incoming materials
Concrete paving blocks (UNE-EN 1338)
Concrete pavers must meet the requirements of UNE-EN 1338. What to check:
- CE marking and declaration of performance (DoP): mandatory with every delivery under Regulation (EU) 305/2011; they certify the declared characteristics.
- Dimensions and thickness: deviation from the nominal size must not exceed the permitted tolerance; thickness must match the load category (6, 8, 10 or 12 cm).
- Colour and surface: uniformity within the batch, checking for damage and spalling.
- Abrasion resistance and weathering durability: stated in the declaration of performance; order the class matching the expected exposure (in the inland comarcas, with occasional light frosts, a higher durability class is advisable).
- Laying pattern: the format must match the design; for special units, check the proportions.
Crushed stone and sub-base materials
- Aggregate to UNE-EN 13242 – checking the fraction (0/32, 0/45, etc.).
- Grading: on the delivery note or with a laboratory report.
- Cleanliness: mud, clay and organic matter are not permitted; check visually as well.
- Moisture content: the optimum moisture range is needed at placing for proper compaction.
Kerb units (UNE-EN 1340)
- Dimensions, thickness, breaking strength.
- CE marking, declaration of performance.
- Checking for surface damage and cracks.
Bedding material
- 2/5 or 4/8 grit, clean, without a fine sandy fraction.
- Laboratory verification of the grading is recommended.
2. Checking the formation and the sub-base
Checking the formation level
After shaping the formation – before spreading the sub-base – check:
- Levels and falls: with a laser level or rotating laser, minimum 2% crossfall away from the building.
- Bearing capacity: with a plate load test (Ev2 modulus) or another recognised test method; the design value must be reached.
- Uniformity: no settlement, soft spots or areas contaminated with fines are permitted.
- Drainage: is any standing water left?
Sub-base – intermediate inspection before covering
An inspection record of covered-up work must be produced for every layer that will be hidden. On completion of the sub-base, check:
- Layer thickness: by core sample or probing; any deviation from the design thickness is documented.
- Compaction: degree of compaction referenced to the Proctor test, or a plate load test (Ev2 modulus).
- Grading: if there was a laboratory test, the report is attached.
- Levels and falls: the basis for the level check after the bedding layer.
- Kerb stability: hardening of the concrete bed, presence of the haunching, levels.
| Test | Method | Acceptance criterion |
|---|---|---|
| Bearing capacity (formation) | Ev2 modulus (plate load test) | Minimum design value |
| Compaction (sub-base) | Proctor test, nuclear density gauge | ≥ 95–98% (per design) |
| Thickness | Core sample, probing | Nominal ± permitted deviation |
| Levels | Laser levelling | ± 1–2 cm (per design) |
| Fall | Laser levelling | Min. 2% crossfall |
3. Checking the finished pavement
Surface regularity
- 4 m straightedge: on public works the permitted deviation is typically ≤ 10 mm; on private jobs, per the tolerance agreed with the client.
- Stepping between units: the height difference between adjacent blocks must not exceed the accepted threshold (stricter on accessible routes).
- Rocking blocks: every rocking unit must be relaid and its joint refilled.
Falls and drainage
- Measure the falls on the finished surface as well – do they match the design?
- Check for ponding in rain or with a hose test.
- Check the connection of channels and gullies.
Joints and jointing
- Is the joint width as designed (generally 3–5 mm)?
- Is the jointing material filled to full depth?
- Top up any empty or washed-out joint sections.
- With polymeric jointing material, re-inspect after the curing time has passed.
Kerbs
- Level retention, junction with the blocks.
- Stability – any rocking or displacement?
- Has the concrete haunching hardened?
Cuts and junctions
- Cut blocks should not be smaller than 1/3 of a unit (especially in trafficked zones).
- Does the area around utility covers sit evenly?
- Accuracy of junctions with building plinths and gates.
4. Documentation – what to keep, and how?
Documentation is not only mandatory (on public works) – it protects the interests of both the client and the contractor. If a dispute arises, documentation is the only objective evidence.
| Document | When is it produced? | What does it contain? |
|---|---|---|
| Material certificate / DoP | At delivery | CE marking, declared performance |
| Delivery note | Every delivery | Quantity, fraction, date |
| Laboratory report | As needed | Grading, Proctor, strength |
| Compaction test record | After the sub-base | Ev2 or degree-of-compaction values |
| Covered-work inspection record | Before covering each layer | Layer thickness, material, level, signature |
| Topographic survey | Finished pavement | Levels and falls with XYZ coordinates |
| Photo documentation | Every phase | Formation, sub-base, kerb, finished surface |
| Handover record | At the end of the works | Description, snags, warranty, signatures |
What to photograph
Phases that should always be recorded:
- Formation level – after compaction, before covering.
- Geotextile / geogrid – if present, condition as laid.
- Sub-base – layers during spreading and after compaction.
- Kerbs with their concrete bed – before covering.
- Bedding layer – even spreading.
- Block laying – during the work, with the pattern visible.
- Jointing and compaction.
- Finished pavement, channels, gullies, kerb junctions.
- Junctions at utility covers.
- Junctions with building plinths and gates.
5. Handover and warranty
The handover procedure
- Site walk-through with the client: inspecting every area.
- Recording snags and defects in the handover record – with a deadline and a responsible party.
- Handing over the documentation: material certificates, test records, photographs.
- Written warranty statement.
- Signatures: by both parties.
Follow-up inspection
The joint material can still settle in the first weeks after laying. Recommended:
- Check the jointing after 2–4 weeks and top up if needed.
- After the first heavy autumn rains, a level check – look for wash-out or settlement.
- On busy areas, return within six months to a year and check the joint condition.